End of March ’18 – Progress is being made

The walls of the 1st story are to roof height and the floors are now being floated with concrete which will take until mid-April. We hope the roof will be on by the end of April and the building will be watertight for the rainy season. At least the new intake will be able to start in October while we […]

Letters from the Children

Penelope and Rod Sharman took out over 50 letters from our sponsors, and brought over a hundred back which we are busy getting out to you now. Sadly these are not replies as they were only two days in Bo so dropped your letters off and picked up the children’s which had already been written.

Senior Secondary School Build – update 16th March

We have just received the pictures (below) of the foundations in which the six classrooms and verandah are just about discernible. A further £10,000 is on its way to pay for the floating of the floors with concrete and the building of the walls. When pictures that this work is underway are received we will send a further £5,000 for […]